[200WILLIAM-EC SP67851] Cladding Scedule
cscl at optusnet.com.au
cscl at optusnet.com.au
Tue May 27 09:37:01 AEST 2025
Thanks Matt,
Would you please check if New Life require entry to any apartment and if that is the case, which? Thank you.
Craig
From: ec <ec-bounces at mailman.perkins.id.au> On Behalf Of matt at perkins.id.au
Sent: Monday, 26 May 2025 4:41 PM
To: M Q Matt Perkins <ec at 200william.com>
Subject: [200WILLIAM-EC SP67851] Cladding Scedule
Hi All,
Follows is the schedule for cladding work from NewLife. Note times might vary with weather, etc.
Warm Regards,
Matt
* Monday 26/5/25
Go to site, site measure and make templates of the Entry Portal Cladding
* Wednesday 4/6/25 - 12/6/25
Remove and replace entry portal.
* 13/6/25 -16/6/25
We will require access to measure all nine levels to site check the sizes, radius and assess any previous water ingress.
* 23/6/25-24/6/25
Start removal Installation of high-level cladding. This will take approx. 2 days per level.
* 26/6/25 - 4/7/25
Complete recladding to 200 WIlliam (eastern facade)
* 7/6/215 - 24/7/25.
Complete high-level cladding to western high-level facade.
P
--
** DO NOT SEND PRIVATE OR CONFIDENTIAL MATERIAL VIA EMAIL
Matt Perkins
0403571333
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.perkins.id.au/pipermail/ec/attachments/20250527/cc93eb3b/attachment.htm>
More information about the ec
mailing list