[200WILLIAM-EC SP67851] Cladding Scedule
matt at perkins.id.au
matt at perkins.id.au
Tue May 27 09:36:44 AEST 2025
Hi Craig,
Yes they will require access to some apartments. Greg has the schedule and will be coordinating with those owners to arrange access over the coming weeks.
Warm Regards
Matt.
P
--
** DO NOT SEND PRIVATE OR CONFIDENTIAL MATERIAL VIA EMAIL
Matt Perkins
0403571333
On 27 May 2025 at 9:34 AM +1000, cscl at optusnet.com.au, wrote:
> Thanks Matt,
> Would you please check if New Life require entry to any apartment and if that is the case, which? Thank you.
> Craig
>
> From: ec <ec-bounces at mailman.perkins.id.au> On Behalf Of matt at perkins.id.au
> Sent: Monday, 26 May 2025 4:41 PM
> To: M Q Matt Perkins <ec at 200william.com>
> Subject: [200WILLIAM-EC SP67851] Cladding Scedule
>
> Hi All,
> Follows is the schedule for cladding work from NewLife. Note times might vary with weather, etc.
>
> Warm Regards,
> Matt
>
>
> • Monday 26/5/25
> Go to site, site measure and make templates of the Entry Portal Cladding
> • Wednesday 4/6/25 - 12/6/25
> Remove and replace entry portal.
> • 13/6/25 -16/6/25
> We will require access to measure all nine levels to site check the sizes, radius and assess any previous water ingress.
> • 23/6/25-24/6/25
> Start removal Installation of high-level cladding. This will take approx. 2 days per level.
> • 26/6/25 - 4/7/25
> Complete recladding to 200 WIlliam (eastern facade)
> • 7/6/215 - 24/7/25.
> Complete high-level cladding to western high-level facade.
>
>
> P
> --
> ** DO NOT SEND PRIVATE OR CONFIDENTIAL MATERIAL VIA EMAIL
> Matt Perkins
> 0403571333
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.perkins.id.au/pipermail/ec/attachments/20250527/5ddf33d6/attachment.htm>
More information about the ec
mailing list