[200WILLIAM-EC SP67851] Cladding Scedule

matt at perkins.id.au matt at perkins.id.au
Mon May 26 16:41:17 AEST 2025


Hi All,
Follows is the schedule for cladding work from NewLife. Note times might vary with weather, etc.

Warm Regards,
Matt


• Monday 26/5/25
Go to site, site measure and make templates of the Entry Portal Cladding
• Wednesday 4/6/25 - 12/6/25
Remove and replace entry portal.
• 13/6/25 -16/6/25
We will require access to measure all nine levels to site check the sizes, radius and assess any previous water ingress.
• 23/6/25-24/6/25
Start removal Installation of high-level cladding. This will take approx. 2 days per level.
• 26/6/25 - 4/7/25
Complete recladding to 200 WIlliam (eastern facade)
• 7/6/215 - 24/7/25.
Complete high-level cladding to western high-level facade.


P
--
** DO NOT SEND PRIVATE OR CONFIDENTIAL MATERIAL VIA EMAIL

Matt Perkins
0403571333
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.perkins.id.au/pipermail/ec/attachments/20250526/422fd4a5/attachment.htm>


More information about the ec mailing list