[200William-EC SP67851] EXT - APARTMENT 601/200 WILLIAM STREET, WOOLLOOMOOLOO COMPLAINTS
Craig Laforest
cscl at optusnet.com.au
Thu Jun 13 10:56:53 AEST 2019
Darren,
I sent another email to you yesterday re BRIS (Patrick asked you to call
them), a contractor I saw several months ago. Have you phoned them because
they said they haven't heard from you?
Regards.
From: Marquis <Marquis at bfms.com.au>
Sent: Thursday, 13 June 2019 9:46 AM
To: Craig Laforest <cscl at optusnet.com.au>; Marquis <Marquis at bfms.com.au>
Cc: 'Patrick Rush' <prush at stratatitle.com.au>; ec at 200william.com
Subject: RE: EXT - APARTMENT 601/200 WILLIAM STREET, WOOLLOOMOOLOO
COMPLAINTS
Hi Craig,
Sorry for the delay getting back to you.
Pooling Water Issue P4
After a number of failed attempts to contact Rescom we have had the system
they installed independently inspected and it is working as designed by AJ
Whipps. Patrick has a contact at Rescom and is trying to arrange a site
inspect through them. Awaiting update.
In the meantime, Tony from Distinction Waterproofing & Remedial (DWRS) will
be onsite tomorrow morning to look at what other options are available eg:
installing a negative waterproofing membrane or concrete injection around
the base of the ramp slab.
Western Terrace Tile Repairs
The damage can't be patched as per Costin Roe recommendation Options 1 or 2.
Cracking of the tile bed has occurred due to water penetration causing
movement of the insulation foam beneath the tile bed. Option 3 was to remove
all and reinstate new including a recommendation to replace the
waterproofing membrane at the same time.
The contractors we have approached are reluctant to take on the work due to
the potential warranty issues. Preservation Technologies will only consider
the works if an independent consultant is engaged to mediate between the two
parties. The tender process will include Preservation Technologies and 2
other qualified contractors to use as comparison.
Proposals Received
Remedial Building & Waterproofing Consultants - $8,260.00 + GST
Note - Includes project management fee based on $70,000.00 + GST total
project cost (7.5%)
Shield Consultants - $8,950.00 + GST
Note - Excludes project management fee Approx. 6.5% total project cost.
Awaiting EC feedback and approval.
Kind regards,
From: Craig Laforest <cscl at optusnet.com.au <mailto:cscl at optusnet.com.au> >
Sent: Tuesday, 11 June 2019 3:38 PM
To: Marquis <Marquis at bfms.com.au <mailto:Marquis at bfms.com.au> >
Cc: 'Patrick Rush' <prush at stratatitle.com.au
<mailto:prush at stratatitle.com.au> >; ec at 200william.com
<mailto:ec at 200william.com>
Subject: EXT - APARTMENT 601/200 WILLIAM STREET, WOOLLOOMOOLOO COMPLAINTS
Darren,
1. On Monday January 21, this year I texted you regarding the water I
have in one of my parking spaces. I also provided pictures of the damage.
The water is increasing and you have not, after many requests, provided me
with a final answer as to what you are doing about the issue. Another text
sent to you on June 7 without the courtesy of any response from you. Almost
6 months since my initial email of January 21 to you and the water is in my
space and next door's space! Any response now as to when I will see the
problem rectified?
2. Level 7 uplifting of western tiles. Again, where are we with this
situation? The tiles are raised and the engineer advised months ago we
should have the whole deck replaced. And once again, I attach pictures,
taken today June 11, 2019. Any response from you Darren at this point?
Craig Laforest
601/200 William Street
Woolloomooloo
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20190613/08fbc129/attachment-0001.html
More information about the EC
mailing list