[200William-EC SP67851] Payment invoice

Matt Perkins matt at spectrum.com.au
Tue Mar 27 12:13:54 AEDT 2018


I thought I agreed to this one already but in case I missed it yes agreed 

Matt



-- 
/* Matt Perkins
       Direct 1300 137 379     Spectrum Networks Ptd. Ltd.
       Office 1300 133 299     matt at spectrum.com.au
       Fax    1300 133 255     Level 6, 350 George Street Sydney 2000
      SIP 1300137379 at sip.spectrum.com.au
       Google Talk MattAPerkins at gmail.com
       PGP/GNUPG Public Key can be found at  http://pgp.mit.edu
*/

> On 27 Mar 2018, at 10:48 am, Patrick Rush <prush at stratatitle.com.au> wrote:
> 
> Thanks for your responses Robin and Brook.
>  
> We will proceed with payment.
>  
> Kind regards
>  
> Alesha Fripp
> Locum Community Manager
>  
> From: Robin Patrick [mailto:robin.j.patrick at gmail.com] 
> Sent: Tuesday, 27 March 2018 10:39 AM
> To: Patrick Rush <prush at stratatitle.com.au>
> Cc: Craig Laforest <craigstephenlaforest at gmail.com>; ec at 200william.com; ec-bounces at 200william.com; Brendan Fang <brendanj at stratatitle.com.au>
> Subject: Re: [200William-EC SP67851] Payment invoice
>  
> Agree 
>  
> On Tue., 27 Mar. 2018, 7:26 am Patrick Rush, <prush at stratatitle.com.au> wrote:
> Good Morning Committee Members,
>  
> I wish to follow up approval of the below mentioned variation for additional labour hours.
>  
> Can the remaining committee members please confirm their approval to proceed with payment?
>  
> Kind regards
>  
> Alesha Fripp
> Locum Community Manager
>  
> From: Craig Laforest [mailto:craigstephenlaforest at gmail.com] 
> Sent: Friday, 16 March 2018 12:56 AM
> To: ec at 200william.com; ec-bounces at 200william.com; Patrick Rush <prush at stratatitle.com.au>
> Subject: Payment invoice
>  
> To the EC committee and Patrick,
>  
> I agree to the payment of the $2,736.
>  
> Craig Laforest
>  
> -----------------------------------------------------------------------------
>  
>  
> Good result. 
>  
> Good to pay.
>  
> Thanks Ken West
> On 15 Mar 2018, at 9:33 PM, Patrick Rush <prush at stratatitle.com.au> wrote:
>  
> Dear Committee,
>  
> See below details from Tanaz of Strat Engineering Solutions about a variation for additional labour hours based on the work carried out by the contractor that removed the rest of the soil from the rooftop. See attached images of the state of the rooftop on Monday 12th March 2018.
>  
> 1
> Tilers cost 2 men x 8 hrs @ $90 / hr
> $1,440.00
> 2
> Membrane Applicators cost 1 man x 8 hrs @ $90 / hr
> $   720.00
> 3
> Material Handling cost 2 men x 4 hrs @ $72 / hr
> $   576.00
>  
> Total not inc GST
> $2,736.00
>  
>  
> Attached is the invoice for the removal of this soil.
> 
> Can you advise if you are happy for me to pay in full or would you like to deduct some of the below costs form the attached invoice?
>  
> Please also note that Preservation Technologies will not know if the damage to the insulation, means that addition insulation is required as they may have enough insulation to finish the project. If a further variation is required I will advise the Committee and seek approval.
>  
>  
> Kind regards,
> 
> Patrick Rush
> Regional Manager
>  
> Phone: (02) 9266 2600 | Direct Phone: (02) 9266 2695 | Email: prush at stratatitle.com.au | Address: PO Box 2727, Taren Point, NSW 2229
>  
> <image001.jpg>    <image002.png>    <image003.png>    <image004.png>    <image005.png>    <image006.png>
>  
> Emailed Communication / Documents Disclaimer
> STM Limited takes no responsibility for content included in this email when relating to a client matter. 
> Please view Vesture’s full email communication disclaimer on our website – www.stratatitle.com.au/disclaimer/
> Important Notice:  Owners should be aware that all correspondence, including letters, facsimile transmissions and emails are retained on the file of your scheme and may be subject to inspection by owners and residents within your scheme, as well as prospective purchasers for any lot that may be for sale within your scheme. As such author discretion is advised.
>  
> From: Tanaz Dhondy [mailto:tanaz.dhondy at costinroe.com.au] 
> Sent: Wednesday, 14 March 2018 12:06 PM
> To: Patrick Rush <prush at stratatitle.com.au>; Marquis <Marquis at bfms.com.au>
> Subject: RE: SP 67851 - URGENT Site Condition and Delays Due to Soil Removal at 200 Williams St, Woolloomooloo
>  
> CO12765.00
> 200 William St, Woolloomooloo
>  
> Hi Patrick, 
>  
> The insulation was also damaged onsite during the soil removal. Prestech currently presume there will be enough insulation to finish the works, but we will only find out once the insulation is installed. If they run short they will require to order more, which would be a variation to the SC to replace the insulation which was broken during the soil removal.
>  
> The variation as a result of the soil removal and associated delays are only for labour affected during the day.
>  
> There are no other variations at this point. 
>  
> Regards,
> Tanaz
>  
>  
>  
>  
> --
> Craig Laforest
> _______________________________________________
> EC mailing list
> EC at 200william.com
> http://200william.com/mailman/listinfo/ec
> _______________________________________________
> EC mailing list
> EC at 200william.com
> http://200william.com/mailman/listinfo/ec
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20180327/c280b77b/attachment-0001.html 


More information about the EC mailing list