Hi Maxine,

 

I would like to acknowledge your letter dated 19th of March 2013 related
to the following Ref: MW:AL:SP67851

 

First of all I want to express my disapproval in relation to the timing
given to attend the building in order to renew the security cards.
Residents yes its fine they are in the building and they can attend, but
when you look after a great N. of apartment for owner investors, sure
you don't expect that a property manager will be attending the building
at that time, unless the strata pays for the overtime that they will be
charging to attend outside the working hours.

 

Please respond and looking forward for alternative hours.

 

 

From: ec-bounces at 200william.com [mailto:ec-bounces at 200william.com] On
Behalf Of Matt Perkins
Sent: Thursday, 21 March 2013 12:53 PM
To: ec at 200william.com
Subject: Re: [200William-EC] Propose Foyer & Lift upgrades

 

Im a Yes to both pending final colour approval.

Matt.

 On 20/03/13 3:50 PM, Shane Ellis wrote:

	Hi All, after reviewing at last nights meeting, I have a revised
Quote as per below. 

	Can we get votes on each level perhaps. ie: if you could all
reply, as follows:

	 

	Upgrade Level E: Yes/No

	Upgrade Level G: Yes/No

	 

	UPGRADE LEVEL E:

	*Paint to purple Mosaic columns outside = $400

	*Paint ceiling throughout Foyer = $1,150

	*Demolish & remove purple fabric = $150

	*Place arced framing, instead of existing angles at above wall =
$1,250

	*Place full height tiles to above at removed fabric
(28m2*$80/m2) = $2,240

	*Supply above high quality tiles (28m2*$80/m2) = $2,240

	TOTAL LEVEL E UPGRADE = $7,430+GST = $8,173

	*No allowance to replace light fittings

	 

	UPGRADE LEVEL G:

	*Demolish and remove existing floor finishes = $1,900

	*Install new floor finishes (25m2*$80/m2) = $2,000

	*Supply above high quality finishes (25m2*$80/m2) = $2,000

	*Remove colonial skirtings & Architraves, and square-set wall
finishes = $800

	*Repaint all of Foyer = $1,800

	*Less Insurance rebate (-$2,400)

	TOTAL LEVEL E UPGRADE = $6,100+GST = $6,710

	 

	 

	*Total for both Lobby areas = $15,423

	 

	 

	
	Best Regards
	Shane Ellis
	0423 000 221
	
	
	
	

	 

	On 19/03/2013, at 5:29 PM, Shane Ellis
<shane at ellisconstructions.com.au> wrote:

	 

	Hi All,  

	For discussion at Meeting, please find below indicative costs to
upgrade finishes at Lifts and at Level E+G foyers. 

	Costs are fully inclusive of all material supply, design fees,
etc.

	I believe we should be able to tap the 'Sinking Fund' for the
costs. The existing style is very dated.

	 

	UPGRADE LEVEL E:

	*Paint to purple Mosaic columns outside = $400

	*Paint ceiling throughout Foyer = $1,150

	*Demolish & remove purple fabric = $150

	*Place arced framing, instead of existing angles at above wall =
$1,250

	*Place full height tiles to above at removed fabric
(28m2*$80/m2) = $2,240

	*Supply above high quality tiles (28m2*$80/m2) = $2,240

	TOTAL LEVEL E UPGRADE = $7,430+GST = $8,173

	 

	 

	UPGRADE LEVEL G:

	*Demolish and remove existing floor finishes = $1,900

	*Install new floor finishes (25m2*$80/m2) = $2,000

	*Supply above high quality finishes (25m2*$80/m2) = $2,000

	*Remove colonial skirtings & Architraves, and square-set wall
finishes = $800

	*Repaint all of Foyer = $1,800

	TOTAL LEVEL E UPGRADE = $8,500+GST = $9,350

	*OPTION to frame Western foyer wall, add arced frame to corner,
and tile extent of wall = $4,510 Inc Tile supply & GST.

	*OPTION to tile wall opposite to lift walls = $4,400

	 

	 

	UPGRADE ELEVATORS:

	*Remove 2 downlights and plug holes = $200*2 = $400

	*Rub back clear finish to timber panels = $950*2 = $1,900

	*Apply new stain to timber panels = $850*2 = $1,700

	TOTAL ELEVATORS UPGRADE = $4,000+GST = $4,450

	 

	*Total for all 3 areas = $21,973

	*Total including Options for Level G tiled walls = $30,883

	 

	These are pricing for my company to undertake the works. 

	I believe that these are competitive costs, and that we will get
alot of 'bang for our buck' - as we can get high quality finishes
without the need to engage an architect or designer.

	 

	re quality of work, below is a link to a recently completed
project of mine.
http://www.brettboardman.com/FoxJohnstonArchitects_QueensParkHouse_WEB/

	 

	 

	Best Regards
	Shane Ellis
	0423 000 221
	
	
	
	

	 

	_______________________________________________
	EC mailing list
	EC at 200william.com
	http://200william.com/mailman/listinfo/ec

	 

	
	
	
	

	_______________________________________________
	EC mailing list
	EC at 200william.com
	http://200william.com/mailman/listinfo/ec






-- 
/* Matt Perkins 
        Direct 1300 137 379     Spectrum Networks Ptd. Ltd. 
        Office 1300 133 299     matt at spectrum.com.au 
        Fax    1300 133 255     Level 6, 350 George Street Sydney 2000
        SIP 1300137379 at sip.spectrum.com.au 
        PGP/GNUPG Public Key can be found at  http://pgp.mit.edu 
*/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20130321/d19de659/attachment-0001.html 


More information about the EC mailing list