Hi All, I was going to brief everyone on the commercial foyer on level G
at the meeting but as that has been delayed I thought it prudent to give
an update.
At the moment there is a few ongoing painting activities that need to be
completed within the building These include fire certification
rectification on a few different levels and also the repair of the level
3 foyer that was badly damaged due to a water leak in a level 4
apartment condenser unit. As part of Darren organizing that work I ask
him to get a quote for the repair and repaint of the commercial foyer on
level G.
As we know the level G entry way forms part of the commercial strata as
such it is not under out control. I proposed to Arnold some months back
that the commercial strata rectify that foyer however at the time the
were not interested. They also have an issue where they are still with
STM and as such cant organize at meeting or really make any decisions
at all as such it stalled.
Darren returned a quote of around $3k to repair and repaint that foyer
and recently I proposed to Arnold that the 3k~ quote be accepted within
the BMC. As it only requires the support of the two BMC members and
would not require the support of the whole commercial strata i thought
it may be a quick path to get the work done and at least share some of
the costs with the commercial strata as part of our standard split.
Arnold has since agreed to do the work within the BMC so this should be
able to go ahead with the rest of the painting which will freshen that
entry way up some what. I think that's a very good outcome considering
we were considering paying for the entire work ourselves.
Kind regards