[200WILLIAM-EC SP67851] Building report
kylie Curtis
kyliemcurtis at yahoo.com
Fri Dec 15 15:39:02 AEDT 2023
Thank you Matt.
Will the engineer follow up with quotes for the works that need to be carried out immediately?
It looks like there’s a lot of work to be carried out and I note the images and points around rust and moisture in the facade and building but I don’t see anything about concrete cancer, unless I’m missing something?
Warm Regards,
Kylie
Sent from my iPhone
> On 15 Dec 2023, at 3:02 pm, matt at perkins.id.au wrote:
>
>
> Hi All,
> You can download the building report from the included link. It's to big for email. There's nothing unexpected there that I can see. I have ask Sarah to follow up and get a quote for the work to generate the technical spec for rectification which can be used for the tender process.
>
> Warm regards
> Matt
>
> https://www.dropbox.com/scl/fi/q5pt0me38tq9nnzbzn663/200-William-Street-Woolloomooloo-Building-Condition-Assessment.pdf?rlkey=pw5w47r3vfn4alod7hj10ah5m&dl=0
>
>
> Matt -- ** DO NOT SEND PRIVATE OR CONFIDENTIAL MATERIAL VIA EMAIL Matt Perkins 0403571333
> --
> ec mailing list
> ec at mailman.perkins.id.au
> http://mailman.perkins.id.au/cgi-bin/mailman/listinfo/ec
More information about the ec
mailing list