Dear Committee,

See the below update with the storm water and sewer system upgrades –

Hi Leo,

Confirming that my steel contractor will be submitting his schedule/proposal for your approval, by Monday latest.
If this is approved, the aim is to have the platforms installed by the end of January.

Regards,

Charlie Assaf
Project Manager

[cid:image002.png at 01D374FD.5BB20E60]

I can also confirm that as part of the tender, there was a accost to clean the car park area affected by the leak from the storm water and sewer systems.


Kind regards,
Patrick Rush
Senior Community Manager

Phone: (02) 9266 2600 | Direct Phone: (02) 9266 2695 | Email: prush at stratatitle.com.au<mailto:northshore at stratatitle.com.au> | Address: PO Box 2727, Taren Point, NSW 2229

[cid:image005.jpg at 01D369EE.1C1641F0]<http://www.stratatitle.com.au/>
**Please note our office will close from COB Thu, 21 Dec and reopen Mon, 8 Jan.

Follow us on LinkedIn<http://www.linkedin.com/company/strata-title-management-stm> | Facebook<http://www.facebook.com/StrataTitleManagement>

Emailed Communication / Documents Disclaimer
STM takes no responsibility for content included in this email when relating to a client matter.
Please view Smarter Communities’ full email communication disclaimer at http://www.smartercommunities.com.au/disclaimer<http://www.smartercommunities.com.au/disclaimer/>

From: Patrick Rush
Sent: Monday, 11 December 2017 9:40 PM
To: ec at 200william.com
Cc: Marquis <Marquis at bfms.com.au>
Subject: DP 1040255 - Storm Water & Sewer System Rectification in P4 Car Park

Hi Robin,

The update provided on Friday 1st December 2017 is below -

The remedial solution has not yet been completely implemented, hence the prevalence of water ingress in the concerned location. The water ingress rectification works are due to be completed next week, and the remedial building works in the pit are scheduled to completed soon after.


I have requested a further update and will provide the response from AJ Whipps Consulting and Rescom Builders and will advise on their response once received.


Kind regards,
Patrick Rush
Senior Community Manager

Phone: (02) 9266 2600 | Direct Phone: (02) 9266 2695 | Email: prush at stratatitle.com.au<mailto:northshore at stratatitle.com.au> | Address: PO Box 2727, Taren Point, NSW 2229

[cid:image005.jpg at 01D369EE.1C1641F0]<http://www.stratatitle.com.au/>
**Please note our office will close from COB Thu, 21 Dec and reopen Mon, 8 Jan.

Follow us on LinkedIn<http://www.linkedin.com/company/strata-title-management-stm> | Facebook<http://www.facebook.com/StrataTitleManagement>

Emailed Communication / Documents Disclaimer
STM takes no responsibility for content included in this email when relating to a client matter.
Please view Smarter Communities’ full email communication disclaimer at http://www.smartercommunities.com.au/disclaimer<http://www.smartercommunities.com.au/disclaimer/>


-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20171214/64854c9e/attachment-0001.html 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 10516 bytes
Desc: image002.png
Url : http://200william.com/mailman/private/ec/attachments/20171214/64854c9e/attachment-0001.png 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.jpg
Type: image/jpeg
Size: 13929 bytes
Desc: image003.jpg
Url : http://200william.com/mailman/private/ec/attachments/20171214/64854c9e/attachment-0001.jpg 


More information about the EC mailing list