[200William-EC SP67851] DP 1040255 - Storm Water & Sewer System Rectification in P4 Car Park

Matt Perkins matt at spectrum.com.au
Tue Dec 12 08:18:33 AEDT 2017


Hi Patrick, 
Perhaps we can get an update give that time line it would be due to be finished this week. Can we find out if they are on track. 

Matt


Sent from my iPad

> On 11 Dec 2017, at 21:39, Patrick Rush <prush at stratatitle.com.au> wrote:
> 
> Hi Robin,
>  
> The update provided on Friday 1st December 2017 is below -
>  
> The remedial solution has not yet been completely implemented, hence the prevalence of water ingress in the concerned location. The water ingress rectification works are due to be completed next week, and the remedial building works in the pit are scheduled to completed soon after.
>  
>  
> I have requested a further update and will provide the response from AJ Whipps Consulting and Rescom Builders and will advise on their response once received.
>  
>  
> 
> Kind regards,
> 
> Patrick Rush
> Senior Community Manager
>  
> Phone: (02) 9266 2600 | Direct Phone: (02) 9266 2695 | Email: prush at stratatitle.com.au | Address: PO Box 2727, Taren Point, NSW 2229
>  
> <image001.jpg>
> **Please note our office will close from COB Thu, 21 Dec and reopen Mon, 8 Jan.
>  
> Follow us on LinkedIn | Facebook
>  
> Emailed Communication / Documents Disclaimer
> STM takes no responsibility for content included in this email when relating to a client matter. 
> Please view Smarter Communities’ full email communication disclaimer at http://www.smartercommunities.com.au/disclaimer
>  
>  
> 
> _______________________________________________
> EC mailing list
> EC at 200william.com
> http://200william.com/mailman/listinfo/ec
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20171212/6706a443/attachment.html 


More information about the EC mailing list