I back Barney's response. 

Regards,
Edward

Sent from my iPhone

> On 2 Nov. 2016, at 9:46 am, Barney Kitay <barnet at kitays.com> wrote:
> 
> I agree,
> We cannot just allow drilling without an evaluation of the location of each hole, taking rebar and other factors into account.
> If this is in place I support the drilling of the holes.
>  
>  
>  
> Kind regards
>  
> Barney 
> M  +61 (0)400 200 446 
> E   barnet at kitays.com
>  
> From: ec-bounces at 200william.com [mailto:ec-bounces at 200william.com] On Behalf Of Matt Perkins
> Sent: 01 November 2016 16:20
> To: Patrick Rush <prush at stratatitle.com.au>; ec at 200william.com
> Subject: Re: [200William-EC SP67851] SP 67851 - DP 1040255 - Core Hole Drilling (FRA5449 - 203, 200 William Street, Woolloomooloo, NSW)
>  
> I was not aware The Act made a determination between the reason common property was being modified.
> 
> I have no objections to the contractor completing the work once the building engineer determines there is no conflict between building hydraulic and electrical services and the proposed drill site. 
> 
> Matt.
>  
> 
> 
> 
> On 1/11/16 4:02 pm, Patrick Rush wrote:
> Hi Matt,
> 
> This is not to modify common property to complete renovations, this is for the contractor replacing the flooring that was water damaged in the Lot wanting to core drill holes to make sure all moisture has been removed before installing the replacement floor boards.
> 
> The core holes will be repaired after moisture readings have been taken.
>  
>  
> 
> Kind regards,
> 
> Patrick Rush
> Strata Manager
>  
> Phone: (02) 9266 2600 | Email: prush at stratatitle.com.au | Address: PO Box 2727, Taren Point, NSW 2229
>  
> <image001.png>        <image002.png>    <image002.png>    <image002.png>     <image002.png>     <image002.png>
>  
> Emailed Communication / Documents Disclaimer
> STM Limited takes no responsibility for content included in this email when relating to a client matter. 
> Please view Vesture’s full email communication disclaimer on our website –www.stratatitle.com.au/disclaimer/
> Important Notice:  Owners should be aware that all correspondence, including letters, facsimile transmissions and emails are retained on the file of your scheme and may be subject to inspection by owners and residents within your scheme, as well as prospective purchasers for any lot that may be for sale within your scheme. As such author discretion is advised.
>  
>  
> From: ec-bounces at 200william.com [mailto:ec-bounces at 200william.com] On Behalf Of Matt Perkins
> Sent: Tuesday, 1 November 2016 3:58 PM
> To: ec at 200william.com
> Subject: Re: [200William-EC SP67851] SP 67851 - DP 1040255 - Core Hole Drilling (FRA5449 - 203, 200 William Street, Woolloomooloo, NSW)
>  
> Hi Patrick,
>  Why would an owner wanting to modify common property not require an exclusive use bylaw ?
> 
> Can you please clarify ?
> 
> Matt
> 
> On 1/11/16 3:53 pm, Patrick Rush wrote:
> Dear Committee,
>  
> Can you please provide approval for the below and attached required work for Core Hole Drilling and repairs to the concrete slab of Unit 203 to repair/replace the water damaged floorboards through the Owners contents insurer’s contractor?
>  
> From my point of view I do not see any issues with the below and attached request as long as any damage caused due to the core hole drilling is rectified.
>  
> Please advise?
>  
>  
> 
> Kind regards,
> 
> Patrick Rush
> Strata Manager
>  
> Phone: (02) 9266 2600 | Email: prush at stratatitle.com.au | Address: PO Box 2727, Taren Point, NSW 2229
>  
> <image001.png>        <image002.png>    <image002.png>    <image002.png>     <image002.png>     <image002.png>
>  
> Emailed Communication / Documents Disclaimer
> STM Limited takes no responsibility for content included in this email when relating to a client matter. 
> Please view Vesture’s full email communication disclaimer on our website –www.stratatitle.com.au/disclaimer/
> Important Notice:  Owners should be aware that all correspondence, including letters, facsimile transmissions and emails are retained on the file of your scheme and may be subject to inspection by owners and residents within your scheme, as well as prospective purchasers for any lot that may be for sale within your scheme. As such author discretion is advised.
>  
>  
> From: Peni Ulu-sua [mailto:pulusua.fra at gmail.com] 
> Sent: Thursday, 27 October 2016 12:17 PM
> To: 'Mark zwolsman' <zwolsee at hotmail.com>
> Cc: Patrick Rush <prush at stratatitle.com.au>
> Subject: RE: DP 1040255 - Core Hole Drilling (FRA5449 - 203, 200 William Street, Woolloomooloo, NSW)
>  
> Good morning  Mark
>  
> Just in regards to the drilling of holes for core testing this process is common and will not affect the structure of the  build in any case and we drill and insert a core sleeve that then seals up the hole drilled 1cm W x 8 cm L and new flooring is laid on top of sleeves.
>  
>  
> Kind Regards,
>  
> Peni Ulu-Sua
> Claims Manager
>  
> Flood Restoration Australia
> 34 Keysborough Close,
> Keysborough, VIC, 3173
> Ph :   1300 66 76 92
> <image003.jpg>
> “The Science of Drying”
> Web: www.fra.com.au
>  
> <image004.jpg>
> <image005.jpg><image006.jpg> <image007.jpg>
>  
>  
>  
> From: Mark zwolsman [mailto:zwolsee at hotmail.com] 
> Sent: Wednesday, 26 October, 2016 9:15 AM
> To: pulusua.fra at gmail.com
> Cc: Patrick Rush <prush at stratatitle.com.au>
> Subject: Re: DP 1040255 - Core Hole Drilling (FRA5449 - 203, 200 William Street, Woolloomooloo, NSW)
>  
> Hi Peni,
>  
> See below response from my Strata manager. Can you confirm what FRA would plan to do with the core drilled holes after you have the required measurements to bring this slab back to pre-existing conditions? What is the remediation process for repairing these or is there any requirement given the size of these holes?
>  
> Regards
>  
> Mark Zwolsman
> 0431013878 
>  
>  
>  
> From: Patrick Rush <prush at stratatitle.com.au>
> Sent: Tuesday, 25 October 2016 7:29 PM
> To: 'Mark zwolsman'
> Subject: RE: DP 1040255 - Core Hole Drilling (FRA5449 - 203, 200 William Street, Woolloomooloo, NSW)
>  
> Hi Mark,
> 
> Can you confirm what the contractors plan to do with the core drilled holes after the have the required measurements?
>  
> Will they be repairing these?
>  
>  
> Kind regards,
> Patrick Rush
> Strata Manager
>  
> Phone: (02) 9266 2600 | Email: prush at stratatitle.com.au | Address: PO Box 2727, Taren Point, NSW 2229
>  
> <image008.png>        <image009.png>    <image010.png>    <image011.png>    <image012.png>    <image013.png>
>  
> Emailed Communication / Documents Disclaimer
> STM Limited takes no responsibility for content included in this email when relating to a client matter. 
> Please view Vesture’s full email communication disclaimer on our website – www.stratatitle.com.au/disclaimer/
> Important Notice:  Owners should be aware that all correspondence, including letters, facsimile transmissions and emails are retained on the file of your scheme and may be subject to inspection by owners and residents within your scheme, as well as prospective purchasers for any lot that may be for sale within your scheme. As such author discretion is advised.
>  
> From: Mark zwolsman [mailto:zwolsee at hotmail.com] 
> Sent: Thursday, 13 October 2016 11:08 AM
> To: Patrick Rush
> Subject: FW: FRA5449 - 203, 200 William Street, Woolloomooloo, NSW
>  
> 
> Patrick,
>  
> FRA have requested they need to wait for approval from Stata to install drying equipment as the sub floor is structure which is not part of my contents and owned by Strata. Can we get approval from Strata to undertake these works asap please.
>  
> Thanks
> 
> Mark Zwolsman
> 0431013878 
> 
> From: pulusua.fra at gmail.com
> To: zwolsee at hotmail.com
> Subject: FRA5449 - 203, 200 William Street, Woolloomooloo, NSW
> Date: Thu, 13 Oct 2016 10:33:58 +1100
>  
>  
> Kind Regards,
>  
> Peni Ulu-Sua
> Claims Manager
>  
> Flood Restoration Australia
> 34 Keysborough Close,
> Keysborough, VIC, 3173
> Ph :   1300 66 76 92
> <image003.jpg>
> “The Science of Drying”
> Web: www.fra.com.au
>  
> <image004.jpg>
> <image005.jpg><image006.jpg> <image007.jpg>
>  
> 
> 
> 
> 
> _______________________________________________
> EC mailing list
> EC at 200william.com
> http://200william.com/mailman/listinfo/ec
>  
>  
> -- 
> /* Matt Perkins 
>         Direct 1300 137 379        Spectrum Networks Ptd. Ltd. 
>         Office 1300 133 299        matt at spectrum.com.au 
>                                    Level 6, 350 George Street Sydney 2000
>         Spectrum Networks is a member of the Communications Alliance & TIO  
> */
>  
>  
> -- 
> /* Matt Perkins 
>         Direct 1300 137 379        Spectrum Networks Ptd. Ltd. 
>         Office 1300 133 299        matt at spectrum.com.au 
>                                    Level 6, 350 George Street Sydney 2000
>         Spectrum Networks is a member of the Communications Alliance & TIO  
> */
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://200william.com/mailman/private/ec/attachments/20161102/916939e3/attachment-0001.html 


More information about the EC mailing list